Most of the pavement in the closure has been removed and the contractor continues processing the concrete and the asphalt to re-use. The new storm sewer installation and the removal of the existing storm sewer continues. The new water main installation from Dugdale to Lewis will continue this week. The sheet piling for the retaining wall next to the forest preserve is in and the concrete cap will be added soon. Major grading operations are expected this week to get the base to the proper elevation so aggregate subgrade can be placed.