The excavation at the roundabout is almost complete and the subgrade will be complete in the next day or two. The storm sewer and watermain in the closure is complete and the crews are now working along 14th St east of Dugdale under daily lane closures. The retaining wall along the forest preserve will be complete in the next week. The concrete curb & gutter and sidewalk installation just started and will take a few weeks to complete. The eastbound lanes of 14th street have been resurfaced and traffic will be shifted onto them within the next week. The curb & gutter, sidewalk, and driveway removals at Jackson have been done and the storm sewer work is starting. Once that is complete the temp pavement will be installed so traffic can be shifted and the pavement work can begin.

A traffic shift is expected this week. Please use caution.

Temporary sidewalks will be provided at Jackson this week for garbage collection. We apologize for any inconvenience this week.