The roundabout subgrade work is complete. The curb and gutter will be complete in a day or two. The asphalt placement has started today with the first of three layers. We are hoping to finish the first lift tomorrow and complete the second lift by the end of the week. The retaining wall at the Forest Preserve is complete except for the fence that will be installed on top of the wall. Other work this week will be grading for the sidewalk and bike path, installation of driveways along Dugdale, some sidewalk installation, light pole foundation and conduit installation, and traffic signal work at Green Bay Road. Storm sewer work between Dugdale and Lewis will continue and the new water main will be fully connected this week.