The roundabout paving is complete. The curb & gutter and driveways at Dugdale are in place. All of the colored concrete for the roundabout apron and the islands is complete. The contractor is installing the street lights, grading behind the curb for the sidewalk and bike path, pouring sidewalk, paving the bike path, landscaping, and installing signs. Storm sewer work is ongoing at Jackson and 14th.

The road is scheduled to be opened on Monday, Nov 4th at 7am.