The roundabout paving should be complete today. The colored concrete still needs to be poured for the roundabout apron and the islands. Once the paving is complete, we will be grading behind the curb for the sidewalk and bike path, installing driveways along Dugdale, pouring sidewalk, paving the bike path, landscaping, and then installing signs. We are also installing the light pole foundations and conduit and upgrading the traffic signal system at Green Bay Road. Storm sewer work between Dugdale and Lewis will finish this week and the crew will move to Jackson and 14th. The new water main is installed and the old water main has been abandoned and filled.