The roundabout is open. There will still be work in the area so please drive carefully and watch for workers. We will be working on installing erosion control measures over the next week and on sidewalk and landscaping as the weather allows. There are still lane closures near Green Bay Road so the contractor can continue to work on the sidewalk and the traffic signal.

The driveways that were excavated to install the storm sewer and water main will be covered with asphalt as a temporary measure for the winter. The sidewalks that were removed near Jackson will also be replaced with asphalt for the winter. These will be replaced with the final product in 2020. The stone trenches in Lewis, Carter, Renken, Glenn, and Jackson will be excavated and asphalt patches will be installed to provide a smooth surface through the winter.

The intersection of Jackson and 14th will be temporarily widened this week to accommodate the future stage changes that are necessary for the reconstruction of the intersection.