14th St construction is progressing nicely. Most of the pavement in the closure has been removed and the contractor is processing the concrete and the asphalt to re-use. The new storm sewer installation and the removal of the existing storm sewer has started. The new water main is installed from Green Bay Rd through Dugdale and this section will be cleaned and tested in the next week. Topsoil has been stripped on most of the work zone and it is being stockpiled for later use.

The construction documentation camera is active and can be viewed from the link on the right side of the screen.