The work is almost complete. The permanent striping was installed a few weeks ago, the permanent traffic signals were activated yesterday and the temporary signals were removed, the topsoil has been placed (although it still needs to be prepared), and the lights should be on throughout the project tonight.

The contractor expects the landscaper to be on site within a week to begin tilling the topsoil and getting rid of the weeds in preparation for sod placement once we get to September. There will also be various punch list work throughout the project over the next few weeks.

Installing additional drainage

Permanent Striping

Removing temporary traffic signals

Placing topsoil