Update: November 16, 2020
We are attempting to get the site ready for the winter. Our last concrete pour for the year was done last week and our final day of asphalt paving is expected tomorrow.Read More…
We are attempting to get the site ready for the winter. Our last concrete pour for the year was done last week and our final day of asphalt paving is expected tomorrow.Read More…
The contractor will begin paving the Jackson intersection, the north side of 14th from Greenfield to Jackson, and the southeast corner of Lewis to Kemble on Monday. The plan is to completeRead More…
The new asphalt has been placed on the north side of 14th from Dugdale to west of Greenfield. Traffic is now on the new pavement from Dugdale to Elmwood and then weavesRead More…
Significant progress has been made since the last post. Asphalt has been placed on the north side of 14th from Dugdale to west of Greenfield. The water main installation for Waukegan andRead More…
Significant progress has been made this week. The majority of the aggregate base has been placed from Dugdale to east of Hervey on the north half of the road. We will placeRead More…
Work has resumed and substantial progress has been made. The new Waukegan water main is live and all work on it has been completed. The new North Chicago water main is inRead More…
The project was shut down for several weeks due to multiple issues. First, the EPA approval of the water main testing took a little longer than usual and then the contractor lostRead More…
Work has temporarily halted while the contractor waits for the test results of the newly installed water main. Once the tests are approved, the contractor will begin installing new services to theRead More…