Update: October 14, 2021
The landscaping is substantially complete. There are several areas that still need to be landscaped and they are on the punch list. The sign installation was delayed due to utility locate issuesRead More…
The landscaping is substantially complete. There are several areas that still need to be landscaped and they are on the punch list. The sign installation was delayed due to utility locate issuesRead More…
The landscaping installation has been progressing throughout September. The perennial plants in the roundabout circle are in place. We hope to have all of the landscaping work complete by the end ofRead More…
The work is almost complete. The permanent striping was installed a few weeks ago, the permanent traffic signals were activated yesterday and the temporary signals were removed, the topsoil has been placedRead More…
As anyone who has driven the site recently knows, the end of the project appears near! The contractor has placed all of the surface course asphalt and the permanent striping is scheduledRead More…
The contractor continues to pour the sidewalk and driveways from Lewis to Jackson on the south side of 14th and we anticipate completing them by the end of next week. The asphaltRead More…
The contractor has completed the asphalt base course. All sidewalks, driveways, curb, and bus pads west of Lewis have been completed. The multi-use path and all driveways are complete north of 14thRead More…
The contractor has completed the curb and gutter and is waiting for the required cure time prior to placing the remaining asphalt. We expect the last of the pavement (other than surface)Read More…
A lot of work has been accomplished in the last two weeks. The last of the storm sewer work was completed yesterday. All of the roadway excavation was also finished yesterday. TheRead More…
The contractor is back after the winter shutdown. We have been installing underground foundations for the new street lights for a few days. We anticipate the pavement removal on the south sideRead More…