ComEd and North Shore Gas are relocating their lines to avoid our construction. They are working in stages to clear the Dugdale and 14th St intersection first. Once they get relocated, they will move to the east and their next section of the relocation. At that point the contractors for AT&T, Comcast, and G4S will begin to relocate their lines near Dugdale and 14th.

The general contractor will start their pavement work when they are confident that we can minimize the full closure at Dugdale and the detour. We are expecting to start the pavement reconstruction work in July.

The contractor will begin working on tree removal, new watermain installation, and temporary traffic signal installation in the next few weeks. This work is not impacted by the utility work.