05Nov/19

Update: November 5, 2019

The roundabout is open. There will still be work in the area so please drive carefully and watch for workers. We will be working on installing erosion control measures over the next week and on sidewalk and landscaping as the weather allows. There are still lane closures near Green Bay Road so the contractor can continue to work on the sidewalk and the traffic signal.

The driveways that were excavated to install the storm sewer and water main will be covered with asphalt as a temporary measure for the winter. The sidewalks that were removed near Jackson will also be replaced with asphalt for the winter. These will be replaced with the final product in 2020. The stone trenches in Lewis, Carter, Renken, Glenn, and Jackson will be excavated and asphalt patches will be installed to provide a smooth surface through the winter.

The intersection of Jackson and 14th will be temporarily widened this week to accommodate the future stage changes that are necessary for the reconstruction of the intersection.

29Oct/19

Update: October 29, 2019

The roundabout paving is complete. The curb & gutter and driveways at Dugdale are in place. All of the colored concrete for the roundabout apron and the islands is complete. The contractor is installing the street lights, grading behind the curb for the sidewalk and bike path, pouring sidewalk, paving the bike path, landscaping, and installing signs. Storm sewer work is ongoing at Jackson and 14th.

The road is scheduled to be opened on Monday, Nov 4th at 7am.

17Oct/19

Update: October 17, 2019

The roundabout paving should be complete today. The colored concrete still needs to be poured for the roundabout apron and the islands. Once the paving is complete, we will be grading behind the curb for the sidewalk and bike path, installing driveways along Dugdale, pouring sidewalk, paving the bike path, landscaping, and then installing signs. We are also installing the light pole foundations and conduit and upgrading the traffic signal system at Green Bay Road. Storm sewer work between Dugdale and Lewis will finish this week and the crew will move to Jackson and 14th. The new water main is installed and the old water main has been abandoned and filled.

06Oct/19

Update: October 6, 2019

The roundabout subgrade work is complete. The curb and gutter will be complete in a day or two. The asphalt placement has started today with the first of three layers. We are hoping to finish the first lift tomorrow and complete the second lift by the end of the week. The retaining wall at the Forest Preserve is complete except for the fence that will be installed on top of the wall. Other work this week will be grading for the sidewalk and bike path, installation of driveways along Dugdale, some sidewalk installation, light pole foundation and conduit installation, and traffic signal work at Green Bay Road. Storm sewer work between Dugdale and Lewis will continue and the new water main will be fully connected this week.

 

 

26Sep/19

Update: September 26, 2019

 

The excavation at the roundabout is almost complete and the subgrade will be complete in the next day or two. The storm sewer and watermain in the closure is complete and the crews are now working along 14th St east of Dugdale under daily lane closures. The retaining wall along the forest preserve will be complete in the next week. The concrete curb & gutter and sidewalk installation just started and will take a few weeks to complete. The eastbound lanes of 14th street have been resurfaced and traffic will be shifted onto them within the next week. The curb & gutter, sidewalk, and driveway removals at Jackson have been done and the storm sewer work is starting. Once that is complete the temp pavement will be installed so traffic can be shifted and the pavement work can begin.

A traffic shift is expected this week. Please use caution.

Temporary sidewalks will be provided at Jackson this week for garbage collection. We apologize for any inconvenience this week.

 

03Sep/19

Update September 3, 2019

 

Most of the pavement in the closure has been removed and the contractor continues processing the concrete and the asphalt to re-use. The new storm sewer installation and the removal of the existing storm sewer continues. The new water main installation from Dugdale to Lewis will continue this week. The sheet piling for the retaining wall next to the forest preserve is in and the concrete cap will be added soon. Major grading operations are expected this week to get the base to the proper elevation so aggregate subgrade can be placed.

 

21Aug/19

Update: August 21, 2019

14th St construction is progressing nicely. Most of the pavement in the closure has been removed and the contractor is processing the concrete and the asphalt to re-use. The new storm sewer installation and the removal of the existing storm sewer has started. The new water main is installed from Green Bay Rd through Dugdale and this section will be cleaned and tested in the next week. Topsoil has been stripped on most of the work zone and it is being stockpiled for later use.

The construction documentation camera is active and can be viewed from the link on the right side of the screen.

 

23Jul/19

Update : 14th Street at Dugdale Street to Close for Roundabout Construction

view as a webpage

Road Closures


14th Street at Dugdale Street to Close for Roundabout Construction

North Chicago/Waukegan, IL- The Lake County Division of Transportation (LCDOT) will be closing 14th Street at Dugdale Street beginning Monday, August 5 at 5 a.m. The closure will last approximately 90 days while the existing four-way stop intersection is converted to a roundabout.  When the road reopens, motorists will be driving through the new roundabout. Please follow the signed detour routes.

Detour Routes:

Detour Route for Pulaski Drive at IL Route 131/Green Bay Road:
IL Route 131/Green Bay Road south, to Martin Luther King Jr. Drive east, to Lewis Ave. north, to 14th Street.

Detour Route for 14th Street and Dugdale Street:
Lewis Ave. south, to Martin Luther King Jr. Drive west, to IL Route 131/Green Bay Road north.

Local traffic will have access to residences and businesses, from all directions, within the closure area.

14th-street_detours map